HA-25/B/20/IIa. That string of letters and numbers appears on orders, quotes, delivery notes and invoices, and yet the person ordering it and the person supplying it don't always read it the same way. This article explains what each part means under the Código Estructural (Spain's Structural Code), what has changed compared with the EHE-08 (the previous Spanish concrete code), specifically that "IIa" at the end, and the most common mistakes made when carrying the designation from the specification to the order and from the order to the batching plant.
The format: T-R/C/TM/A
Section 33.6 of the Código Estructural (Real Decreto 470/2021, the Spanish Structural Code) sets out that concrete is classified using this format, which must appear on the drawings and in the project specification:
| Part | What it indicates | In the example |
|---|---|---|
| T | Type of concrete: HM for plain, HA for reinforced, HP for prestressed. HRM or HRA if it contains recycled aggregate. | HA: reinforced concrete |
| R | Specified characteristic compressive strength, in N/mm², at 28 days on a cylindrical specimen. | 25 N/mm² |
| C | Initial letter of the consistence: S, P, B, F or L. AC if self-compacting. | B: soft |
| TM | Maximum aggregate size, in millimetres. | 20 mm |
| A | Environment designation (exposure class). | IIa, which is now written as an X class |
Strength: the number everyone looks at
The strength is the specified characteristic value, not the average you will actually obtain. The Code recommends the series 20, 25, 30, 35, 40, 45, 50, 55, 60, 70, 80, 90 and 100, and sets two minimums worth remembering when quoting (section 33.4):
- 20 N/mm² for plain concrete only.
- 25 N/mm² as a minimum for reinforced or prestressed concrete.
That is why there is no structural "HA-20". If someone asks you for one, it is most likely an ordering error or a non-structural concrete, and it is worth clarifying before loading. Above 50 N/mm² we speak of high-strength concrete, and with recycled aggregate the maximum is 40 N/mm².
Consistence: what to expect from the cone
The consistence letter corresponds to a slump range in the Abrams cone (table 33.5.a), and a tolerance of ±10 mm is accepted on receipt (table 57.5.2.2):
| Consistence | Slump | Range accepted on receipt |
|---|---|---|
| Dry (S) | 0-20 mm | 0-30 mm |
| Plastic (P) | 30-40 mm | 20-50 mm |
| Soft (B) | 50-90 mm | 40-100 mm |
| Fluid (F) | 100-150 mm | 90-160 mm |
| Liquid (L) | 160-210 mm | 150-220 mm |
Two provisions of the Code change what you order in practice: unless justified, dry and plastic consistences are not used, and for columns, floor slabs and beams in buildings, fluid consistence is used unless there is justification otherwise. Liquid is only valid if achieved with superplasticisers. The specification may also set the consistence by the numerical slump value instead of by the letter.
For self-compacting concrete the letter is replaced by AC, and it can be refined with the classes for slump-flow, viscosity, passing ability and segregation resistance (tables 33.6.a to 33.6.d).
Maximum aggregate size
TM is the maximum aggregate size in millimetres, defined in section 30.3. For the plant it has a practical consequence: the Code requires the aggregate to be made up of at least two grading fractions for maximum sizes of up to 22 mm, and three for larger sizes (section 51.3.2.3). In other words, changing the TM may mean changing the hoppers that go into the mix, not just the name of the product.
The environment: from IIa to the X classes
This is the change that causes the most confusion. The EHE-08 used classes such as I, IIa, IIb, IIIa or IV. The Código Estructural keeps the format, but the A is taken from table 27.1.a, which uses the European exposure classes:
- X0: no risk of corrosion.
- XC1 to XC4: carbonation. For example, XC2 is "wet, rarely dry", such as foundations in non-aggressive soils.
- XD1 to XD3: chlorides of non-marine origin, such as swimming pools or car park slabs.
- XS1 to XS3: marine environment.
- XF1 to XF4: freeze-thaw.
- XA1 to XA3: chemical attack.
- XM1 to XM3: abrasion.
So a 25 N/mm² reinforced concrete, soft consistence, with 20 mm aggregate for a foundation could be designated, for example, HA-25/B/20/XC2. But the class is chosen by the project according to the element and its surroundings, and an element may be subject to a combination of classes (section 11.2). The Code does not include an equivalence table between the old and new classes, so don't translate them on your own: if an order arrives with the old nomenclature, ask for the class in the specification.
The exposure class is not decoration: the minimum cement content and the maximum water/cement ratio depend on it (table 43.2.1.a), and in some classes so do the documentation and tests you will be asked for.
Common mistakes when ordering and supplying
- Ordering by strength only. Section 51.3.4 requires the purchaser to state, as a minimum, consistence, maximum aggregate size, exposure class, strength (or cement content if designated by dosage) and whether it will be plain, reinforced or prestressed.
- Products with a trade name and no designation. The delivery note must show the full designation (Annex 4).
- Duplicate mixes with the same name and a different exposure class, which end up being loaded in place of one another.
- Changing the consistence on site with water. This is prohibited; only an admixture is allowed, following an approved procedure (section 51.4.2).
- Price lists with old designations that no longer match what the specifications ask for.
Each designation with its mix and its cost
In Gesthorm, each concrete mix or recipe is stored with its raw material composition, and the application calculates its cost per cubic metre using what the raw material and its transport really cost you. When a delivery note arrives from the batching plant, Gesthorm takes the cost of the mix and the selling price the job has in its quote, and records the raw materials used.
That lets you see what it really costs to move from one exposure class to a more demanding one, or from soft to fluid, and to quote using that figure. It is explained in the cost per cubic metre by mix, and if your plants use different loading programs, in several plants in a single program.