XC4 exposure class and X classes for concrete (Código Estructural)

What XC4 and the other X exposure classes mean under the Código Estructural, which replaced the EHE-08, and what changes in paperwork, testing and delivery notes.

Gesthorm team · Infonet Consultores5 min read

Concrete batching plant with aggregate hoppers and cement silos under a cloudy sky

The Código Estructural (Spain's Structural Code) has been in force since November 2021, but many plants still run on a mix of EHE-08 paperwork, formulas and habits. From the point of view of a concrete batching plant, this article summarises what the change of regulation brought: what is now named differently, which documents you need to have ready, which tests are required and what data the delivery note must carry. It is no substitute for reading the Code itself, but it works as a checklist to see whether your plant is up to date.

Which regulation it is and when it applies

Real Decreto 470/2021, of 29 June (Royal Decree 470/2021), approves the Código Estructural. It was published in the BOE (Spain's Official State Gazette) on 10 August 2021 and came into force on 10 November 2021. Its repealing provision repeals Real Decreto 1247/2008 (Royal Decree 1247/2008), which approved the EHE-08 (the former Spanish Structural Concrete Instruction), and the one covering the Instrucción de Acero Estructural (EAE, the Spanish Structural Steel Instruction). Since publication it has had only one correction of errors, in the BOE of 2 February 2024.

The transitional provision excluded projects commissioned before it came into force, provided the works started within one year (building) or three (civil engineering). Those deadlines have now passed, so today any works you supply will normally be governed by the Código Estructural.

The plant's production control is still regulated by Real Decreto 163/2019 (Royal Decree 163/2019), which predates the Code and cites EHE-08 articles. To find out how those references are interpreted in your inspections, the safest course is to ask your certification body.

Exposure classes become the X classes

The most visible change is in the designation. The Code keeps the T-R/C/TM/A format from section 33.6, but the A (the environment) is expressed with the exposure classes in table 27.1.a, the same letters used in the Eurocodes:

  • X0: no risk of corrosion.
  • XC1 to XC4: corrosion caused by carbonation.
  • XD1 to XD3: chlorides of non-marine origin.
  • XS1 to XS3: chlorides of marine origin.
  • XF1 to XF4: freeze-thaw.
  • XA1 to XA3: chemical attack.
  • XM1 to XM3: erosion or abrasion.

For the plant this has direct consequences: product names in the loading software, price lists, quotes and delivery notes have to speak the same language as the specifications. If you still have products with IIa or IIIa in the name, check which X class they correspond to on each job, because the equivalence is not automatic: it depends on the element and its surroundings, and it is decided by the project.

Consistencies and other mix design details

Section 33.5 keeps the slump-based consistencies (dry, plastic, soft, fluid and liquid) and adds guidance that affects the plant's day-to-day work:

  • Unless justified, dry and plastic consistencies are not used, and liquid is only accepted if achieved with superplasticisers.
  • In building work, fluid consistency is used for columns, slabs and beams unless justified otherwise.
  • Self-compacting concrete has its own designation (AC instead of the consistency letter) and its own specific tests.
  • Concrete with recycled aggregate is designated HRM or HRA, with a maximum characteristic strength of 40 N/mm².
  • The maximum cement content is 500 kg/m³ unless authorised, and the minimum content and the maximum water/cement ratio depend on the exposure class (table 43.2.1.a).

Documentation before supply

Annex 4 of the Code sets out the documentation that accompanies each product. For concrete without an officially recognised quality mark, the supplier provides a declaration of compliance (declaración responsable) before supply to each job, listing the concretes to be delivered, their nominal mix design and a series of commitments. Among them:

  • For XA, XS, XD, XF and XM environments, having checked water impermeability, with a report less than six months old.
  • For XF2 and XF4, having checked the entrained air content, also with a report less than six months old.
  • For XC3, XC4, XD, XS, XF, XA and XM, keeping available to the user a technical data sheet for each working formula, with the materials (cement, aggregates, admixtures, water, additions) and the nominal mix design with its tolerances. Each sheet carries a unique reference that later appears on the delivery notes.
  • Giving prior notice of any change of supplier of the component materials.

If the concrete has an officially recognised quality mark, the mark's documentation is enough (section 1.2 of Annex 4).

During supply and at the end

There are four points worth keeping under control:

  1. The delivery sheet has a minimum content set out in Annex 4: besides the usual details, the actual mix design (type and content of cement, water/cement ratio, additions and admixtures), the technical data sheet reference in demanding environments and the latest time of use of the concrete.
  2. Durability tests: without a quality mark, the water penetration test at the start and every six months per mix design type in XA, XS, XD, XF or XM environments, and the entrained air test with the same frequency in XF2 and XF4 (section 57.5.7).
  3. The automated plant: section 57.1 requires the batching to be recorded with a device linked to the weighbridge, or with certificates from the manufacturer of the batching software and from the concrete manufacturer guaranteeing data traceability. Real Decreto 163/2019 already required this.
  4. The final certificate: when supply to a job ends, the manufacturer draws up a certificate of the concretes supplied, with types and quantities (section 57.6). For long supply contracts, monthly partial certificates can be issued.

The Code also insists that adding water on site is prohibited. If the slump falls below the specified value, the only option is to add plasticiser or superplasticiser, following a written procedure approved by the manufacturer and authorised by the site management (section 51.4.2).

Quick checklist for your plant

  • Products, price lists and quotes named with the X exposure classes.
  • Declaration of compliance, or quality mark documentation, ready for each job.
  • Technical data sheet with a unique reference for each formula used in demanding environments.
  • Delivery note showing the actual mix design and the latest time of use.
  • Six-monthly water penetration and entrained air tests up to date, if they apply to you.
  • Final certificate for each job, with types and quantities, easy to produce without redoing it by hand.

Where Gesthorm helps

A good part of the above depends on having the data for each load in order. Gesthorm imports from the batching system the outgoing delivery notes with their raw material consumption, and stores each formula with its composition, so you have in one place what was ordered, what was loaded and for which job. Incoming delivery notes also arrive automatically, so you know which supplier delivered each raw material.

With custom reports you can pull, for example, all the concrete supplied to a job by type and quantity, or all the loads of a formula over a given period. And if you have several plants with different batching systems, everything sits in the same database. See how the connection with the plants works, and the rest in Gesthorm's features.