How to Prepare a Concrete Tender for a Large Construction Project

What to check in the specification, how to cost each concrete mix and the haulage, which terms to put in writing and how to assess customer risk.

Gesthorm team · Infonet Consultores4 min read

Aerial view of a large hospital construction site with several tower cranes and concrete structures under construction

On a small job, a price per cubic metre and little else is usually enough. On a large project, with thousands of cubic metres, several types of concrete and months of supply, a mistake of just a few euros per cubic metre turns into a lot of money, and a customer who pays late can leave you with a hole in your cash flow. This article walks through the steps for preparing that tender with real data: what to read in the specification, how to calculate the cost, which terms to put in writing and how to assess the risk.

Step 1: what to extract from the specification

Before putting a single price down, extract the following from the project and the specification:

  • Concrete types and volumes for each one: the full designation, with strength, consistence, maximum aggregate size and exposure class.
  • Additional requirements: special cement type, self-compacting concrete, fibre-reinforced concrete, quality mark, colour.
  • Deadlines and pace: when it starts, how long it lasts and what maximum volume per day or per pour is expected.
  • Quality control: how strength will be checked and which durability tests are required for the exposure class.
  • Placing on site: pump, chute or skip, access routes and the site's unloading restrictions.

The Código Estructural (Spain's Structural Code), section 51.3.4, requires the purchaser to specify to you, before supply, at least the consistence, the maximum aggregate size, the exposure class, the characteristic strength (or the cement content if the concrete is designated by mix proportions), any special cement characteristics and whether the concrete will be plain, reinforced or prestressed. If the specification does not make this clear, ask in writing before tendering.

Step 2: the cost of each type of concrete

For each designation, start from the mix formula you are going to use and calculate its cost per cubic metre using the current purchase prices of each raw material, including the transport of the raw material. Do not use a generic rate: a change of exposure class can raise the minimum cement content and lower the maximum water/cement ratio, and that changes the cost.

Also bear in mind:

  • Seasonal admixtures: if the project runs through summer or winter, the dosage of retarder or accelerator may change.
  • Tests that you will have to carry out as supplier, for example durability tests in demanding environments if you do not hold a quality mark.
  • Minimum volume and surplus: how much returned concrete it is reasonable to expect and who pays for it.

Step 3: haulage

On a large project, haulage can weigh as much as the raw materials. Calculate:

  1. A truck's cycle: loading, outward trip, waiting, unloading, washing out and return.
  2. Trucks needed for the planned pouring rate, bearing in mind that concrete must not exceed an hour and a half between mixing and placing unless retarders are used (section 51.4.1 of the Code).
  3. Cost per trip, whether in-house or subcontracted, and how it is spread per cubic metre.
  4. Foreseeable waiting times and how they will be charged.

If the site is far from the plant, consider which plant serves it best if you have several, or whether an on-site plant would be worthwhile.

Calculate haulage for an intense pouring day, not for the average. If, on a large slab, the site needs a high pace for several hours, that day determines how many trucks you need and whether you have to subcontract. Tendering on the average and running into the problem on the day of the slab is one of the quickest ways to lose money on a large project.

Step 4: building the price

A tidy way to set it out internally, with an example structure (you fill in the figures):

DesignationEstimated volumeRaw material costHaulage costOther costsTender priceMargin
HM-20/B/20/X0m³€/m³€/m³€/m³€/m³%
HA-25/B/20/XC2m³€/m³€/m³€/m³€/m³%
HA-30/F/12/XC4m³€/m³€/m³€/m³€/m³%

Adding up by volume gives the theoretical profitability of the whole project. Look at it as a whole: sometimes a type with a low margin is offset by another with a large volume, and sometimes the "cheap" type is precisely the one that will be supplied the most.

Step 5: the terms to put in writing

  • Validity of the tender and, on long projects, how prices are reviewed if raw materials go up.
  • Price per type and what happens if the project asks for a type that was not in the tender.
  • Waiting times, surplus and part loads: what is included and what is charged separately.
  • Additional services such as pumping, special admixtures or supplies outside the plant's normal working hours.
  • Payment method and terms, and the risk limit beyond which supplies are stopped.

Step 6: assessing the customer's risk

A large project concentrates a lot of money in a single customer. Before tendering, look at how much they already owe you, how long they take to pay on average and what maximum risk you are prepared to take on with them. During the project, make sure the debt does not exceed that limit and that the average collection period does not lengthen month after month. It is easier to stop in time if the limit was written into the tender.

From tender to project in Gesthorm

In Gesthorm you prepare the tender and the application automatically gives you the prices of the tendered items, the theoretical profitability and the customer's maximum risk. Once it is accepted, it generates the corresponding project and, from then on, shows you at every moment the deviation from the tender and the actual profitability, because every delivery note arriving from the batching plant carries its cost according to the formula and its price according to the project.

The cost of each formula per cubic metre updates by itself with every purchase of raw material and its transport, and each customer's risk and average collection period are calculated from what has been invoiced and collected. See the cost per cubic metre and profitability and customer risk and collections.