
A concrete mixer parked at the gate of a site is neither producing nor delivering. If it waits twenty minutes, the next customer receives their load late; if it waits an hour, the concrete may no longer be usable. Waiting time creeps into transport costs unnoticed, because it is almost never measured. This article explains how to measure it, how to put it in your quotation and what to do to reduce it.
Why waiting time matters more than it seems
Waiting time has three effects at once:
- Direct cost: the truck and the driver are tied up without producing anything. If transport is subcontracted, the haulier may charge you for it; if it is your own fleet, you still pay for it in hours.
- Knock-on delays: the truck does not get back in time for the next load, so the plant either needs more trucks than it should, or delays other customers.
- Quality risk: the Código Estructural (Spain's Structural Code, section 51.4.1) sets as a general rule that no more than an hour and a half should pass between adding the mixing water and placing the concrete, unless retarders are used, and in hot weather that period must be shorter. A long wait eats into that margin and can end in rejection or returned concrete.
The Code itself also notes that agreements between the purchaser and the supplier must take into account the time that may elapse between production and placing on site (section 51.4.2). In other words, waiting time is not just a commercial matter.
Which times to measure on each trip
To discuss waiting time using data, break the trip down into stages. It is enough to record four moments for each trip:
| Moment | Who records it |
|---|---|
| Loading time at the plant | Taken from the batching plant's delivery note |
| Arrival time on site | Driver |
| Discharge start time | Driver, signed by the site |
| Discharge end time | Driver, signed by the site |
Waiting time is the time between arrival and the start of discharge. The Código Estructural states that the start of discharge marks the beginning of the delivery and reception period, which lasts until discharge is finished (section 51.4.2). That is why it is worth having those two times signed by the site: they are the ones that end up being disputed.
Nothing sophisticated is needed. A section on the delivery note where the driver notes the times and the site foreman signs is enough to start with.
If transport is subcontracted, ask the haulier to use the same criteria. That way, their waiting-time invoices and yours to the customer come from the same data, and you do not end up paying the haulier for waiting time that you cannot charge to the site because nobody signed for it.
How to agree waiting time with the customer
Waiting time is better discussed before the job than after the invoice. In the quotation, make clear:
- Discharge time included per truck, for example, a number of minutes depending on the volume.
- Price of additional waiting time per time increment, and from when it is counted.
- What happens if the concrete exceeds its time limit for reasons attributable to the site: who bears the cost of the load.
- How waiting time is evidenced: the times recorded and signed on the delivery note.
The specific figures are up to each company and its market. What matters is that they are in writing and that the customer has accepted them. Without that, charging for waiting time usually ends in a discount.
What to do so the mixer waits less
- Plan the pace with the site: ask how many cubic metres per hour they can place (pump, skip, chute) and adjust truck departures to that pace.
- Confirm before loading that the formwork, the pump and the access are ready, especially for the first truck of the day.
- Stagger departures rather than sending all the trucks at once at the start of the day.
- One contact on site who can stop or speed up deliveries by phone.
- Review the sites with the most waiting every month and discuss it with the customer with the data in front of you.
- Use retarders judiciously on distant sites or where waiting is foreseeable, always within what the mix design allows and what the site management accepts.
How to read the waiting-time data
Once you have a few weeks of records, group them as follows:
- By site: see whether a few sites account for most of the lost time.
- By time of day: check whether the first truck in the morning or the last in the afternoon waits longer than the rest.
- By placement method: with a pump, waiting depends on the pump; with a chute, on the pace of the site.
- By driver, not to blame anyone, but to see whether any driver is not recording the times.
With that, you have arguments to renegotiate terms, change the way you schedule or simply invoice what was agreed.
Transport and its cost in Gesthorm
Gesthorm stores, on each delivery note imported from the batching plant, the vehicle and the driver who made the trip, along with the customer and the site. It also manages vehicles, drivers, concrete haulage companies and their prices, and anticipates the invoices that hauliers must send you so that you can compare them with those you receive. It also calculates workers' incentives based on their work reports and the delivery notes they have handled.
If you agree to charge for waiting time, you can invoice it as one more item, because Gesthorm allows invoices based on delivery notes and on free-form items, and then lets you see the real profitability of each site against its quotation. You will find the details in delivery note invoicing and in everything Gesthorm does.


