Every mixer that comes back with concrete still inside is a double cost: you paid for the cement, aggregates, admixtures and transport to produce it, and now you have to pay to get rid of it. Because each return is usually small, rarely does anyone add up what they amount to in a month. This article suggests a simple way to record returned concrete, work out what it costs and tackle the most common causes.
Why concrete comes back to the plant
Before trying to reduce it, it helps to know where it comes from. The most frequent causes are these:
- Surplus from the last truck. The site asks for "one more mixer just in case" and half a cubic metre or more is left over.
- Eyeballed measurements. The foreman estimates the volume without deducting voids or without counting the real thickness of the formwork.
- Site not ready. The truck arrives and the formwork isn't finished, the pump hasn't turned up or there is no access, and the wait ends in a return.
- Rejection on arrival. The consistency is outside tolerance or the concrete has passed its time limit for use.
- Ordering error. A different type is loaded from the one the site needed.
- Breakdown of the pump, the truck or the site itself midway through the pour.
Each cause has a different person responsible and a different solution. That is why the first step is to note down the reason, not just the quantity.
Also separate returned concrete that is reused from concrete that is lost. Half a cubic metre that ends up in a block for the plant itself is not the same as half a cubic metre that goes to washing: the first recovers some of its cost and the second recovers nothing.
What a returned cubic metre really costs
The cost isn't just that of the mix. To calculate it properly, add up:
| Item | Where the data comes from |
|---|---|
| Raw materials in the mix | Cost per cubic metre of the mix loaded |
| Round-trip transport | Price of concrete transport or the cost of your own truck |
| Truck and driver time | Time the truck was unable to make another trip |
| Handling the surplus | Washing, separating aggregates, water, waste management or reuse |
| Lost sale | What has not been invoiced, if returned concrete isn't charged for |
Do the sums with your own numbers. For example, if 30 returns of half a cubic metre come back in a month, that is 15 m³ produced and transported for nothing, plus the cost of dealing with it. Seeing that figure in one place helps get the subject onto the agenda of the monthly meeting.
How to record returns without making it complicated
The record has to be quick or it won't get done. The minimum worth noting in each case:
- Delivery note number of the load it came from.
- Approximate quantity returned, in cubic metres.
- Reason, from a closed list (surplus, rejection, site not ready, ordering error, breakdown). If you leave the reason free-text, you won't be able to group the data.
- Destination it was given.
- Whether it is invoiced or not, according to what was agreed with the customer.
With the delivery note as a reference you already have the customer, the site, the truck, the driver and the mix. There's no need to write them out again.
Review the data every month using the same table: cubic metres returned by reason, by customer and by site, and their cost. After a few months you will have your own benchmark to tell whether a month has been normal or bad, and you will be able to check whether the measures you take are working.
What to do with the concrete that comes back
The options depend on each plant's facilities, but the usual ones are:
- Make non-structural pieces at the plant itself (blocks, barriers, counterweights) if you have moulds and space.
- Recover aggregate and water with a washing installation. The Código Estructural (Spain's Structural Code) requires that transport equipment be washed in basins that allow the water to be recycled (section 51.4.1), and allows recycled water under certain conditions (article 29).
- Manage it as waste, at a cost.
What you cannot do is reload that concrete onto another site as if it were new. The Code limits the time between mixing and placing to an hour and a half, unless retarders are used (section 51.4.1), and prohibits adding water to restore consistency (section 51.4.2).
Measures that reduce returns
- Confirm the last truck. Ask the site to confirm the volume of the last mixer when the one before it is already being poured, rather than loading it in advance.
- Orders based on measurements. On large sites, ask for the measurement of the element and compare it with what was ordered. If it doesn't add up, ask before loading.
- Check that the site is ready before sending the first truck: formwork, pump, access.
- Clear terms in the quote on what happens with surplus and waiting time. If the customer knows returned concrete is invoiced, they order more carefully.
- Review returns by reason every month, with names: the sites, customers and foremen that return the most.
- Tackle rejections from the plant: if there are rejections for consistency, check the moisture of the aggregates, the dosing of admixtures and transport times to that site.
The data you have in Gesthorm
So that the cost calculation doesn't end up in a spreadsheet that nobody updates, you need the real cost of each load. Gesthorm imports from the batching plant every outgoing delivery note with its customer, site, vehicle, driver, item, quantity produced and raw material consumption, and assigns the cost according to the mix. That cost per cubic metre updates by itself with each purchase of raw materials and their transport.
From there you can pull tailored reports by customer, site or period, export them to Excel and cross-check them against your returns record, and see the real profitability of each site against its quote, which is where uncharged returns end up showing. If the plant makes use of surplus, the mass balance and stock features help you keep raw materials under control. You can find the details of the calculation in the cost per cubic metre.